Detailed Interpretation on IEC 62133: 2017+AMD1:2021 (edition 1.1),
CB,
IECEE CB is the first genuine international system for mutual recognition of electrical equipment safety test reports. NCB (National Certification Body) reaches a multilateral agreement, which enables manufacturers to obtain national certification from other member countries under CB scheme on the basis of transferring one of the NCB certificates.
CB certificate is a formal CB scheme document issued by authorized NCB, which is to inform other NCB that the tested product samples conform to present standard requirement.
As a kind of standardized report, CB report lists relevant requirements from IEC standard item by item. CB report not only provides results of all required testing, measurement, verification, inspection and assessment with clearness and non-ambiguity, but also including photos, circuit diagram, pictures and product description. According to the rule of CB scheme, CB report will not take effect until it presents with CB certificate together.
With CB certificate and CB test report, your products can be exported to some countries directly.
The CB certificate can be directly converted to the certificate of its member countries, by providing the CB certificate, test report and difference test report (when applicable) without repeating the test, which can shorten the lead time of certification.
The CB certification test considers the product’s reasonable use and foreseeable safety when misused. The certified product proves the satisfactory of the safety requirements.
● Qualification: MCM is the first authorized CBTL of IEC 62133 standard qualification by TUV RH in mainland China.
● Certification and testing capability: MCM is among the first patch of testing and certification third party for IEC62133 standard, and has finished more than 7000 battery IEC62133 testing and CB reports for global clients.
● Technical support: MCM possesses more than 15 technical engineers specialized in testing as per IEC 62133 standard. MCM provides clients with comprehensive, accurate, closed-loop type of technical support and leading-edge information services.
【Summary of Standard Revision】
This standard is a combination edition of IEC 62133: 2017 and AMD1: 2021, mainly covering four revision parts (refer to below detailed revision content). It is more about the completeness of the original standard, no too much technical revision, therefore, hardly effect testing ability. But changes in some testing terms may affect testing results.
【Revision content】
1、7.1.2: Revision of charging procedure: no implement the revision on cut-off current
of flash charge batteries, but only some text revision and supplement.
7.1.2 Second procedure
This charging procedure applies only to 7.3.1,7.3.4,7.3.5,and 7.3.9.
After stabilization for 1 h-and to 4 h, respectively, at an ambient temperature of the highest test temperature and the lowest test temperature, respectively,as specified in Table 2, cells are charged by using the upper limit charging voltage and maximum charging current, until the charging current is reduced to 0,05 It A, using a constant current to constant voltagecharging method.
IEC62133-2:2017+AMD1:2021 CSV – 15- IEC 2021
NOTE The voltage and current can vary depending upon the temperature range (e.g. between T2 and T3 or between T1 and T4 of Figure A.1).Stabilization time within the specified time range should allow for thermal equilibrium to be reached where possible